Status Update, Week of June 1, 2008

Progress for Week One (June 1, 2008)
Site Engineer staked out building on property.
Call was made to Missouri One Call for stakes to identify existing utilities.
Meetings with subcontractors on details to begin project.
Meeting with Engineer to determine equipment to be used for soil compaction.
Bottom Line: Lots of construction prep work was completed and there are tiny flags all over the property!